PSPO-I practice question 15 of 25
How much time is required after a Sprint to prepare for the next Sprint? (choose the best answer)
Full set: 178 questionsDomain Scrum Theory & Principles
The Scrum framework prescribes a continuous flow of development through consecutive Sprints. The conclusion of one Sprint, marked by the Sprint Retrospective, is immediately followed by the start of the next Sprint with its Sprint Planning event. There are no gaps or intermediate phases between Sprints. This continuous cycle maintains momentum, provides a consistent rhythm for the Scrum Team, and ensures that opportunities to inspect and adapt are never delayed. Activities like backlog refinement and planning for the next Sprint occur during the current Sprint, not in a break between them.
A. The Scrum Guide does not define any break between Sprints. Sprints are designed to be contiguous to maintain a consistent cadence and flow.
B. Product Backlog refinement is an ongoing activity that occurs during a Sprint to prepare for future Sprints, not in a gap between them.
C. All work required to create a "Done" Increment, including testing, must be completed within the Sprint. Spilling work over violates this core principle.
E. Since options A, B, and C describe anti-patterns and contradict the Scrum framework, this option is incorrect.
1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 8. "A new Sprint starts immediately after the conclusion of the previous Sprint."
2. Schwaber, K., & Beedle, M. (2002). Agile Software Development with Scrum. Prentice Hall. p. 26. "Sprints are contiguous. As soon as one Sprint ends, the next Sprint begins."
3. Verheyen, G. (2013). Scrum: A Pocket Guide (A Smart Travel Companion). Van Haren Publishing. p. 59. "There is no time between Sprints. A new Sprint starts immediately after the previous Sprint finishes."
Keep practicing
Take the free PSPO-I practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-I practice questions
- Question 1How often should customer satisfaction be measured? (choose the best answer)
- Question 2True or False: The Scrum Team is accountable for creating a valuable increment every Spri…
- Question 3One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily S…
- Question 4Which outcome is expected as a Scrum Team matures? (choose the best answer)
- Question 5Who must attend the Daily Scrum? (choose the best answer)
- Question 6During a Sprint, when is new work or further decomposition of work added to the Sprint Ba…