PSPO-I practice question 15 of 25

How much time is required after a Sprint to prepare for the next Sprint? (choose the best answer)

Full set: 178 questions

Domain Scrum Theory & Principles

Answer options
A: The break between Sprints is timeboxed to one-week for a one-month Sprint, and usually less for shorter Sprints.
B: Enough time for the requirements for the next Sprint to be determined and documented.
C: Enough time for the Developers to finish the testing from the last Sprint.
D: None. A new Sprint starts immediately following the end of the previous Sprint. Correct answer
E: All of the above are allowed depending on the situation.
Correct Answer:
D. None. A new Sprint starts immediately following the end of the previous Sprint.
Explanation

The Scrum framework prescribes a continuous flow of development through consecutive Sprints. The conclusion of one Sprint, marked by the Sprint Retrospective, is immediately followed by the start of the next Sprint with its Sprint Planning event. There are no gaps or intermediate phases between Sprints. This continuous cycle maintains momentum, provides a consistent rhythm for the Scrum Team, and ensures that opportunities to inspect and adapt are never delayed. Activities like backlog refinement and planning for the next Sprint occur during the current Sprint, not in a break between them.

Why Incorrect

A. The Scrum Guide does not define any break between Sprints. Sprints are designed to be contiguous to maintain a consistent cadence and flow.
B. Product Backlog refinement is an ongoing activity that occurs during a Sprint to prepare for future Sprints, not in a gap between them.
C. All work required to create a "Done" Increment, including testing, must be completed within the Sprint. Spilling work over violates this core principle.
E. Since options A, B, and C describe anti-patterns and contradict the Scrum framework, this option is incorrect.

References

1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. p. 8. "A new Sprint starts immediately after the conclusion of the previous Sprint."

2. Schwaber, K., & Beedle, M. (2002). Agile Software Development with Scrum. Prentice Hall. p. 26. "Sprints are contiguous. As soon as one Sprint ends, the next Sprint begins."

3. Verheyen, G. (2013). Scrum: A Pocket Guide (A Smart Travel Companion). Van Haren Publishing. p. 59. "There is no time between Sprints. A new Sprint starts immediately after the previous Sprint finishes."