PSPO-I practice question 16 of 25

True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?

Full set: 178 questions

Domain Scrum Framework

Answer options
A: True
B: False Correct answer
Correct Answer:
B. False
Explanation

The statement is false. The Product Backlog is an emergent, living artifact that is never complete. According to the Scrum framework, it evolves as the product and the environment in which it will be used evolves. Only the Product Backlog Items (PBIs) that are anticipated for the upcoming Sprint need to be detailed and well-understood by the Scrum Team. Items lower in the order are typically larger and less defined. This practice of just-in-time refinement allows the team to adapt to new knowledge and feedback, which is a core principle of Scrum's empirical approach. Requiring a fully detailed backlog upfront is a characteristic of traditional, plan-driven methodologies, not Scrum.

Why Incorrect

A. True: This is incorrect because it describes a waterfall approach, which contradicts Scrum's principles of empiricism and adaptation. A fully detailed upfront backlog inhibits the ability to respond to change. ---

References

1. Schwaber

K.

& Sutherland

J. (2020). The Scrum Guide. Scrum.org.

Page 10

"Product Backlog" section: "The Product Backlog is an emergent

ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team... The Product Backlog is never complete. It evolves as the product and the environment in which it will be used evolves."

2. Schwaber

K.

& Beedle

M. (2002). Agile Software Development with Scrum. Prentice Hall.

Chapter 5

"The Product Backlog

" Page 70: "The Product Backlog is never complete. At the start

it contains everything that is initially envisioned. The Product Backlog evolves as the product and the environment in which it will be used evolve."

3. Layton

M. C.

& Ostermiller

S. J. (2017). Agile Project Management with Scrum. Dummies. (While a commercial book

it is authored by certified Scrum trainers and reflects official doctrine).

Chapter 6

"Creating the Product Backlog": "Your initial product backlog should contain everything you can think of that your stakeholders might want... Don’t worry about getting everything in the product backlog at the start. The product backlog is a living document." This reinforces that the backlog is not a fixed

fully detailed document from the beginning.