PSPO-II practice question 9 of 10
Organizations should reduce their investment in a product when the product's: (choose the best answer)
Full set: 92 questionsDomain Managing Products with Agility
According to the Evidence-Based Management (EBM) framework, Unrealized Value (UV) measures the potential future value that could be captured if the product perfectly met all customer needs. When a product's Unrealized Value is very small, it indicates that the product has largely saturated its market or that there are very few unmet customer needs left to satisfy. In this scenario, the potential return on investment for new features or innovations is minimal. Therefore, organizations should reduce their investment in developing the product further, often transitioning it to a maintenance state to harvest its Current Value, and redirect their capital toward other products or initiatives that possess a much larger Unrealized Value.
B. Incorrect because a low Current Value combined with a high Unrealized Value might actually warrant increased investment to capture that potential market.
C. Incorrect because high Current Value provides revenue; if Unrealized Value is also high, continued investment is justified to capture more market share.
D. Incorrect because a very large Unrealized Value indicates significant untapped market potential, which is exactly when an organization should increase investment.
E. Incorrect because option A accurately describes the EBM condition under which investment should be reduced due to diminishing returns.
1. Scrum.org. (2020). The Evidence-Based Management Guide. (Section: Key Value Areas - Unrealized Value, p. 8).
2. Scrum.org. (2020). The Evidence-Based Management Guide. (Section: Investment and Value, pp. 7-9).
Keep practicing
Take the free PSPO-II practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-II practice questions
- Question 1What might indicate to a Product Owner that they need to work more with the Scrum Team? (…
- Question 2What are the accountabilities of a Tester on a Scrum Team? (choose the best two answers)
- Question 3Your executive leadership team believes that your product can achieve higher market share…
- Question 4Who is accountable for maintaining and communicating the Product Goal? (choose the best a…
- Question 5Who is accountable for creating a plan for the Sprint and adhering to the Definition of D…
- Question 6If a Scrum Team uses Product Backlog refinement, when should it occur? (choose the best t…