PSPO-II practice question 5 of 10
Who is accountable for creating a plan for the Sprint and adhering to the Definition of Done? (choose the best answer)
Full set: 92 questionsDomain Understanding and Applying the Scrum Framework
According to the Scrum Guide, the Developers are the specific individuals on the Scrum Team who are committed to creating any aspect of a usable Increment each Sprint. The framework explicitly assigns them the accountability for creating a plan for the Sprint (which forms the Sprint Backlog alongside the Sprint Goal and selected items) and for instilling quality by strictly adhering to the Definition of Done. While the entire Scrum Team is accountable for creating a valuable, useful Increment every Sprint, the specific tactical execution, planning of the Sprint's daily work, and technical adherence to quality standards (the Definition of Done) rest solely on the shoulders of the Developers.
A: While the Scrum Team is accountable for the Increment, the specific accountabilities of Sprint planning and adhering to the Definition of Done belong to the Developers. B: The Product Owner is accountable for maximizing product value and managing the Product Backlog, not planning the Sprint's technical execution. C: The Scrum Master is accountable for establishing Scrum and team effectiveness, not for creating the Sprint plan or adhering to technical quality standards. E: Since the Product Owner and Scrum Master do not share these specific execution and quality accountabilities, this option is incorrect.
1. Schwaber
K.
& Sutherland
J.
"The Scrum Guide
" 2020
Section: Developers
p. 5.
Keep practicing
Take the free PSPO-II practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-II practice questions
- Question 1What might indicate to a Product Owner that they need to work more with the Scrum Team? (…
- Question 2What are the accountabilities of a Tester on a Scrum Team? (choose the best two answers)
- Question 3Your executive leadership team believes that your product can achieve higher market share…
- Question 4Who is accountable for maintaining and communicating the Product Goal? (choose the best a…
- Question 6If a Scrum Team uses Product Backlog refinement, when should it occur? (choose the best t…
- Question 7Sharing people with unique skills across multiple teams will likely result in which of th…