PSPO-II practice question 7 of 10
Sharing people with unique skills across multiple teams will likely result in which of the following conditions? (choose the best answer)
Full set: 92 questionsDomain Evolving the Agile Organization
Sharing individuals with unique skills across multiple Scrum Teams creates critical dependencies and bottlenecks. In Agile and Scrum environments, cross-functional teams are designed to have all the competencies needed to accomplish the work without depending on others outside the team. When a specialist is shared, their availability becomes a constraint. If multiple teams require this individual's expertise simultaneously, teams are forced into a waiting state, which disrupts flow, increases cycle time, and ultimately impedes the continuous delivery of value. This context switching also reduces the shared individual's actual efficiency, contrary to traditional resource utilization theories. Therefore, the most likely outcome of sharing unique skills across teams is increased waiting times and delayed value delivery.
B: Scrum Teams are required to be cross-functional and develop the necessary skills internally; relying on shared experts prevents this necessary skill growth. C: While it may seem cheaper on paper, the cost of delay and context switching usually outweighs the perceived financial savings of sharing resources. D: Context switching and bottlenecking actually reduce overall throughput and efficiency, meaning less actual value gets delivered, not more.
1. Schwaber, K., & Sutherland, J. (2020). The Scrum Guide. Scrum.org. (Section: Scrum Team, p. 5 - Cross-functional teams).
2. Reinertsen, D. G. (2009). The Principles of Product Development Flow: Second Generation Lean Product Development. Celeritas Publishing. (Chapter 3: The Economics of Queues).
Keep practicing
Take the free PSPO-II practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other PSPO-II practice questions
- Question 1What might indicate to a Product Owner that they need to work more with the Scrum Team? (…
- Question 2What are the accountabilities of a Tester on a Scrum Team? (choose the best two answers)
- Question 3Your executive leadership team believes that your product can achieve higher market share…
- Question 4Who is accountable for maintaining and communicating the Product Goal? (choose the best a…
- Question 5Who is accountable for creating a plan for the Sprint and adhering to the Definition of D…
- Question 6If a Scrum Team uses Product Backlog refinement, when should it occur? (choose the best t…