RCDDV14.1 practice question 3 of 35

An organization initiates an innovation program to deliver exceptional performance and benefits. After the program transition plan is in place and the implementation of a benefits sustainment plan starts the program manager discovers the program may be shut down due to lack of funding. To ensure continued funding for the program, what should the program manager do next?

Full set: 320 questions
Answer options
A: Complete the benefits sustainment plan and update the benefits register
B: Present a revised ROl to the program sponsors based on the remaining investment.
C: Conduct a cost-benefit analysis to ensure the program sponsors understand the program's long- term benefits
D: Review the program business case and the program's strategic alignment and long-term benefits with the program governance board. Correct answer
Correct Answer:
D. Review the program business case and the program's strategic alignment and long-term benefits with the program governance board.
Explanation

A threat to funding is a strategic issue that must be addressed at the highest level of program oversight. The program manager's most effective action is to engage the program governance board. This involves reviewing the original program business case to re-emphasize the value proposition and demonstrating the program's ongoing alignment with the organization's strategic objectives. By reinforcing the long-term benefits and strategic importance, the program manager provides the governance board with the necessary justification to champion the program and secure continued funding. This action addresses the root cause of the funding threat, which is likely a perceived or actual shift in strategic priorities.

Why Incorrect

A. This is an operational task; it does not address the strategic threat to the program's funding and existence.
B. Presenting a revised ROI is a useful tactic, but it is secondary to re-establishing the program's fundamental strategic value with decision-makers.
C. A cost-benefit analysis is a component of the business case; reviewing the entire strategic context is a more comprehensive and powerful approach.

References

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 2.4.1, Program Strategic Alignment, p. 24.

Project Management Institute. (2017). The Standard for Program Management (4th ed.). Section 4.3, Program Business Case Management, p. 63.