RCDDV14.1 practice question 4 of 35
The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?
Full set: 320 questionsPMI defines programs as collections of related projects managed to obtain benefits aligned with organisational strategic objectives, which ultimately drive shareholder value. Consequently, the program manager verifies that program goals and outcomes map directly to the organisation’s strategic objectives; this alignment confirms contribution to shareholder value.
A. Charter states program purpose but itself must already align with strategy; not authoritative reference for shareholder value.
B. Structures/policies describe governance, not value alignment.
D. Governance plan defines decision rights; it supports, but does not define, strategic alignment.
1. PMI – The Standard for Program Management, 4th ed., §1.2 “Program Management and Strategic Objectives”, pp. 3-5.
2. Milosevic, D. & Martinelli, R. (2016). Program Management for Improved Business Results, 2nd ed., Wiley, Ch. 2, p. 28.
Keep practicing
Take the free RCDDV14.1 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other RCDDV14.1 practice questions
- Question 1A large international manufacturing company is centralizing its IT which is currently spr…
- Question 2Which of the following terms is often used to describe two parallel paths that have ident…
- Question 3An organization initiates an innovation program to deliver exceptional performance and be…
- Question 5The chief executive officer reminds a program manager that a program must deliver a 30% r…
- Question 6An initiative involves the development of new technology and leverages existing technolog…
- Question 7In a transformational program, all projects are on track and delivering their objective. …