RCDDV14.1 practice question 4 of 35

The program manager wants to ensure that a program contributes to shareholder value. The program manager should verify alignment with which of the following?

Full set: 320 questions
Answer options
A: Program charter
B: Organizational structures and policies
C: Organizational strategic objectives Correct answer
D: Program governance plan
Correct Answer:
C. Organizational strategic objectives
Explanation

PMI defines programs as collections of related projects managed to obtain benefits aligned with organisational strategic objectives, which ultimately drive shareholder value. Consequently, the program manager verifies that program goals and outcomes map directly to the organisation’s strategic objectives; this alignment confirms contribution to shareholder value.

Why Incorrect

A. Charter states program purpose but itself must already align with strategy; not authoritative reference for shareholder value.
B. Structures/policies describe governance, not value alignment.
D. Governance plan defines decision rights; it supports, but does not define, strategic alignment.

References

1. PMI – The Standard for Program Management, 4th ed., §1.2 “Program Management and Strategic Objectives”, pp. 3-5.

2. Milosevic, D. & Martinelli, R. (2016). Program Management for Improved Business Results, 2nd ed., Wiley, Ch. 2, p. 28.