Impediments are a part of any project. Which of the following is NOT true about impediments in Scrum?

Full set: 148 questions

Domain Scrum Roles

Answer options
A: They reduce the productivity of a Scrum team.
B: Impediments can be both internal and external.
C: Impediments should be documented only by the team members in the Impediment Log. Correct answer
D: Impediments faced are brought up by the Scrum Team during the Daily Standup Meeting.
Correct Answer:
C. Impediments should be documented only by the team members in the Impediment Log.
Explanation

In Scrum, while any team member can and should identify impediments, the Scrum Master is primarily responsible for ensuring they are resolved and for maintaining the Impediment Log (also known as an Impediment Register). The statement that impediments should be documented only by team members is incorrect. The Scrum Master owns the process of impediment removal, which includes tracking them in the log and facilitating their resolution, often by working with individuals or groups outside the Scrum Team.

Why Incorrect

A. This is true. An impediment is, by definition, an obstacle that slows down or blocks the team, thereby reducing productivity.
B. This is true. Impediments can be internal to the team (e.g., a knowledge gap) or external (e.g., a delayed dependency from another department).
D. This is true. The Daily Standup meeting is a key event where team members are expected to raise any impediments that are blocking their progress.

References

SCRUMstudy, "A Guide to the Scrum Body of Knowledge (SBOK® Guide)," 3rd Edition, 2017. Chapter 7, Section 7.2, "Scrum Master," p. 122.

SCRUMstudy, "A Guide to the Scrum Body of Knowledge (SBOK® Guide)," 3rd Edition, 2017. Chapter 10, Section 10.4, "Daily Standup Meeting," p. 228.