SMC practice question 5 of 25
To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collaborate with each other and the stakeholders to create deliverables that provide the greatest possible value to the customer. This ensures realization of all the following project benefits, EXCEPT:
Full set: 148 questionsDomain Initiate Phase
The statement that collaboration ensures "efficient management of large numbers of Change Requests" is not a primary benefit of Scrum collaboration. Scrum's strength lies in its ability to accommodate and adapt to change through an iterative process and a prioritized backlog, rather than processing a high volume of formal change requests as seen in traditional project management. The goal is to welcome change to deliver maximum value, not to build a bureaucracy for managing numerous formal requests. The other options are direct benefits of the collaborative nature of Scrum.
B. Collaboration within the Scrum Team and with stakeholders is fundamental to transparently identifying, assessing, and mitigating risks throughout the project.
C. The principle of self-organization, enabled by collaboration, allows the team to collectively solve problems and adjust their plan to meet the Sprint Goal.
D. Collaboration is the cornerstone of the Retrospect Sprint meeting, where the team and Scrum Master work together to inspect and adapt their processes for continuous improvement.
ScrumStudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Section 1.4.4, Iterative Development, p. 11. This principle emphasizes that Scrum uses an iterative approach to "better manage changes and build products that satisfy customer needs." It focuses on adaptation, not formal change management systems.
ScrumStudy. (2017). A Guide to the Scrum Body of Knowledge (SBOK® Guide) (3rd ed.). Section 1.4.1, Empirical Process Control, p. 8. The principles of transparency, inspection, and adaptation support the benefits listed in options B, C, and D.
Keep practicing
Take the free SMC practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SMC practice questions
- Question 1Which of the following about User Story Acceptance Criteria is true?
- Question 2You are the Scrum Master for your organization and you are working to create a Developmen…
- Question 3Impediments are a part of any project. Which of the following is NOT true about impedimen…
- Question 4The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort …
- Question 6George is a Scrum Master on a project to develop a Course Management System and Leave Man…
- Question 7Which of the following is NOT an objective of a Retrospect Sprint Meeting?