The Scrum Master is attending a meeting in which the Scrum Team is estimating the effort required to develop the functionality described in each User Story. The team wants to adopt an estimation technique through which they will be able to quickly estimate a large number of User Stories. Which of the following techniques do you think they should adopt?

Full set: 148 questions

Domain Plan and Estimate Phase

Answer options
A: Planning Poker.
B: Wideband Delphi.
C: Affinity Estimation. Correct answer
D: Relative Sizing.
Correct Answer:
C. Affinity Estimation.
Explanation

Affinity Estimation is a technique specifically recommended for quickly estimating a large number of User Stories. In this method, the team members silently place User Stories on a wall under predefined categories or columns representing different effort sizes (e.g., Small, Medium, Large). This parallel and collaborative activity allows for the rapid sizing of an entire backlog, making it much faster than techniques that address one story at a time. It is ideal for the scenario described where speed and volume are key considerations.

Why Incorrect

A. Planning Poker: This is a consensus-based technique that is effective but can be time-consuming as each story is discussed and estimated individually.
B. Wideband Delphi: This is a more formal and iterative estimation method that is generally not suited for rapid estimation of a large volume of items.
D. Relative Sizing: This is a general concept or principle, not a specific technique. Affinity Estimation is one method of implementing relative sizing.