SP-SAFE-PRACTITIONER practice question 17 of 35
What is one element teams present during the draft plan review?
Full set: 269 questionsDuring the Draft Plan Review at the end of Day 1 of PI Planning, each team briefly shows its draft iteration-by-iteration plan. This review explicitly includes the iteration goals that have been formulated for each upcoming iteration, giving other teams and stakeholders quick visibility into intended outcomes and dependencies. (SAFe 6.0, PI Planning article, “Draft Plan Review” section)
Planned business value – Business Owners assign and negotiate business value on Day 2, not during the draft review. Milestones – Milestones are identified at the ART level and summarised in the final plan, not in the team draft review. ART PI risks – Risks discussed in the draft are team-level; consolidated ART PI risks are presented during the final plan review.
1. Scaled Agile Framework (SAFe 6.0). “PI Planning,” Draft Plan Review, para 1–2.
2. Scaled Agile Framework (SAFe 6.0). “Iteration Goals,” definition, para 1.
Keep practicing
Take the free SP-SAFE-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SP-SAFE-PRACTITIONER practice questions
- Question 1During which PI Planning activity do Business Owners assign business value to PI Objectiv…
- Question 2What is an example of an ART event?
- Question 3What is used to capture the current state of the Portfolio and provide input for defining…
- Question 4According to SAFe, a Feature should be sized to fit into what duration?
- Question 5Why do Lean-Agile leaders try to connect the silos of business, software, test, and quali…
- Question 6What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers"…