Which of the following statements describes the Release Train Engineer role?
Full set: 269 questionsThe Release Train Engineer (RTE) is a servant leader and coach for the Agile Release Train (ART). Their primary responsibility is to facilitate ART events and processes and assist the teams in delivering value. The RTE helps guide the train, remove impediments, and foster an environment of continuous improvement, acting as the chief coach for the ART. This role is focused on the process and execution of the ART, not the content or technical aspects.
A. To maintain Team Backlogs: This is the responsibility of the Product Owner, who manages and prioritizes the backlog for their specific Agile Team.
C. To serve as the ART-level content authority: This is the role of Product Management, which is responsible for defining and prioritizing the Features in the ART Backlog.
D. To ensure technical integrity of all development within the ART: This is the responsibility of the System Architect, who provides architectural guidance and technical enablement.
1. Scaled Agile, Inc. (2023). Release Train Engineer. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/release-train-engineer/. (Refer to the "Responsibilities" section, which lists "Coach leaders, teams, and Scrum Masters/Team Coaches in Lean-Agile practices and mindsets.")
2. Scaled Agile, Inc. (2023). SAFe 6.0 Principles. Scaled Agile Framework. Retrieved from https://www.scaledagileframework.com/safe-principles/. (Principle #9, "Decentralize decision-making," distinguishes between content, process, and architectural authority roles.)
Keep practicing
Take the free SP-SAFE-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other SP-SAFE-PRACTITIONER practice questions
- Question 1During which PI Planning activity do Business Owners assign business value to PI Objectiv…
- Question 2What is an example of an ART event?
- Question 3What is used to capture the current state of the Portfolio and provide input for defining…
- Question 4According to SAFe, a Feature should be sized to fit into what duration?
- Question 5Why do Lean-Agile leaders try to connect the silos of business, software, test, and quali…
- Question 6What else does the SAFe principle, "unlock the intrinsic motivation of knowledge workers"…