TM12 practice question 12 of 15
An agile development team decides to hire a tester who has always worked: - in independent test teams, reporting the problems found in a defect…
Full set: 65 questionsIn an agile environment, the role of a tester shifts from a formal gatekeeper to an integrated team collaborator. The primary goal is to provide rapid feedback to developers to ensure the product meets requirements and can be released on time. The tester's background in formal defect reporting and prioritizing quality above all else conflicts with the agile team's focus on speed and budget. Therefore, the most likely successful adaptation is for the tester to change their mission. They would focus on verifying that user stories meet acceptance criteria and communicating findings directly to developers, rather than using a formal defect tracking system for every issue, which aligns with agile principles of direct communication and delivering value quickly.
A. The transition from a highly structured, safety-critical environment to a fast-paced agile one involves a significant cultural and mindset shift; assuming it will happen "without any issue" is unrealistic.
B. Agile teams are self-organizing and collaborative. It is highly unlikely that developers would "immediately follow" guidelines from a new team member whose background conflicts with their established agile practices.
C. Continuing to work in a traditional manner would create significant friction with the agile team's goals and processes, directly undermining their focus on time and budget constraints.
1. ISTQB® Certified Tester Foundation Level Agile Tester Syllabus (CTFL-AT), Version 2014.
Section 2.2.2, The Agile Tester’s Mindset: "In Agile projects, the tester’s mindset should be to... collaborate with developers and business representatives... Testers must understand that on an Agile project, the whole team is responsible for quality." This supports the shift from an independent role to a collaborative one.
Section 3.2.1, Agile Testing Practices: "Rather than waiting for a feature to be completed and then testing it, testers and developers can work together to test a feature as it is being developed... Defects found during this collaborative testing are reported verbally and fixed immediately, without the need for a formal defect management system." This directly supports the rationale for option D.
2. Paasivaara, M., & Lassenius, C. (2014). Agile and Lean in a Multi-site Context: A Case Study. In Lecture Notes in Business Information Processing (Vol. 179, pp. 1-15). Springer.
Section 4.2, Communication and Collaboration: The study highlights that successful agile adoption requires a shift towards "informal communication channels" and co-location to facilitate rapid feedback loops. This contrasts with the formal defect tracking system mentioned in the tester's background and supports the move towards direct verification and communication described in option D.
3. University of Calgary, Schulich School of Engineering, SENG 623: Software Development in Teams, Lecture on Agile Testing.
Course materials emphasize that in agile, testing is not a phase but a continuous activity. The role of the tester is to be a "quality assistant" for the team, focusing on preventing defects through collaboration rather than just finding them after development. This aligns with the mission shift from formal reporting to verifying adherence to requirements collaboratively.
Keep practicing
Take the free TM12 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other TM12 practice questions
- Question 2Which of the following would you expect to be most likely an example of a demotivating fa…
- Question 3Which of the following statements describing the consequences of specifying test conditio…
- Question 7The main objectives the senior management team wants to achieve are: - to reduce the cost…
- Question 8After a selection process you have selected a test management tool that is going be intro…
- Question 9You are performing a quality risk analysis for a CSCI (Computer Software Configuration It…
- Question 10You are a Test Manager working for a software organization where reviews have never been …