AGILEPM-FOUNDATION practice question 13 of 35

During which of the project lifecycle phases should deployment ac'vi'es be added to the plan?

Full set: 150 questions
Answer options
A: Planning phase Correct answer
B: Development phase
C: Delivery phase
D: Deployment phase
Correct Answer:
A. Planning phase
Explanation

In the AgilePM lifecycle, the high-level planning for deployment is conducted during the Foundations phase. A key product of this phase is the Deployment Plan, which outlines the strategy, approach, and schedule for releasing solution increments into operational use. While detailed planning for each specific increment's deployment occurs later, the overall strategy and activities are first added to the plan during Foundations. The option "Planning phase" is the most appropriate generic term for the Foundations phase among the choices provided.

Why Incorrect

B. During the Development phase (Evolutionary Development), detailed deployment tasks for the current increment are planned, but the overall strategy is already set.
C. "Delivery phase" is not an official phase name in the AgilePM project lifecycle.
D. The Deployment phase is when the deployment plan is executed. Planning should be completed before this phase begins.

References

- AgilePM® Agile Project Management Handbook v2.0, DSDM Consortium, 2014, Chapter 5, Section 5.3.3 "Foundations". This section details the objectives of the phase, including establishing the project's plans.

- AgilePM® Agile Project Management Handbook v2.0, DSDM Consortium, 2014, Chapter 15, Section 15.6 "Deployment Plan". This section describes the product and explicitly states it is created during the Foundations phase.