Which technique allows for tes'ng the achievailability of objec'ves?
Full set: 150 questionsTimeboxing is a core AgilePM technique for project control that directly tests the achievability of objectives. By setting a fixed, non-negotiable deadline (the end of the Timebox), the team is forced to focus on delivering a specific set of objectives within that period. If the objectives for a Timebox are consistently not met, it provides immediate feedback that the goals are not achievable as planned, prompting re-assessment of priorities, estimates, or the objectives themselves.
A. Modeling is a technique for understanding and communicating requirements or designs; it does not test the ability of the team to deliver them within a timeframe.
B. A Facilitated Workshop is a collaborative event for planning or problem-solving. It can help define achievable objectives but does not test their implementation.
C. MoSCoW is a prioritisation technique. It helps make a plan achievable by providing contingency (Won't Haves), but it doesn't test the delivery process itself.
APMG International, "AgilePM® Agile Project Management Handbook v2.0," 2014, p. 89. The description of Timeboxing states its purpose is to "keep the team focused on delivery" and "ensure that the project remains on track to deliver on time." This focus on delivery within a fixed period inherently tests achievability.
APMG International, "AgilePM® Agile Project Management Handbook v2.0," 2014, p. 20. Principle 6, "Develop Iteratively," explains that each iteration (often a Timebox) is a feedback cycle, which includes feedback on the process and the achievability of plans.
Keep practicing
Take the free AGILEPM-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-FOUNDATION practice questions
- Question 1Which of the following statements about diverse teams are true? Increased creativity and …
- Question 2Which statement applies to the DSDM process?
- Question 4What role, ideally, should be independent of the outcome to be achieved in a Facilitated …
- Question 5How does the Post-Project phase add value to a project?
- Question 6Which of the following statements about posi've characteris'cs of an effec've change team …
- Question 7Which statement about change is correct for DSDM?