AGILEPM-FOUNDATION practice question 5 of 35

How does the Post-Project phase add value to a project?

Full set: 150 questions
Answer options
A: Define how the operation of the solution will be managed
B: Iteratively explores the low- level detail of the requirements
C: Checks how well the expected business benefits have been met Correct answer
D: Brigs a baseline of the Evolving Solution into operational use
Correct Answer:
C. Checks how well the expected business benefits have been met
Explanation

The Post-Project phase occurs after the final increment of the solution has been deployed. Its primary purpose is to assess the actual business value delivered against the benefits detailed in the Business Case. This phase formally closes the project by confirming whether the project's objectives were met and if the expected return on investment is being realized. It provides crucial feedback for future projects and strategic business decisions. This is the point where the project's success is formally measured from a business perspective.

Why Incorrect

A. This is typically addressed during the Foundations phase (in the Management Approach Definition) and refined during Deployment.
B. This is the core activity of the Evolutionary Development phase, where the solution is built incrementally and iteratively.
D. This is the primary objective of the Deployment phase, which transitions the solution from development into live operational use.

References

- APMG International. (2014). AgilePM® Agile Project Management Handbook v2.0. Chapter 6, "The DSDM Process," p. 36, states, "The Post-Project phase takes place after the last planned Deployment. The purpose of this phase is to assess the business benefits that have accrued from the use of the solution delivered by the project."

- APMG International. (2014). AgilePM® Agile Project Management Handbook v2.0. Appendix A, "The Products," p. 111, describes the Benefits Assessment product, which is created in this phase to "assess the benefits actually accruing from the use of the delivered solution."

Scroll to Top