AGILEPM-FOUNDATION practice question 7 of 35
Which statement about change is correct for DSDM?
Full set: 150 questionsDSDM is founded on the philosophy that in today's business environment, change is a constant. The approach acknowledges that projects operate within a changing world and that trying to freeze requirements at the start is unrealistic and counterproductive. DSDM's iterative and incremental nature, combined with techniques like MoSCoW prioritization and timeboxing, is specifically designed to embrace and manage change effectively. This allows the project to deliver the most valuable features in response to evolving business needs, ensuring the final solution remains relevant.
A. This reflects a traditional waterfall mindset. DSDM assumes requirements will evolve and are not fully definable at the start.
B. DSDM's philosophy is to welcome and manage change to deliver the right solution, not to avoid it.
C. DSDM's use of fixed timeboxes and variable scope makes estimating more manageable in the face of inevitable change.
- APMG International, "AgilePM® Agile Project Management Handbook v2.0," 2014, Chapter 3, Page 13. The handbook states, "DSDM is a response to a changing world... DSDM provides the project framework to enable businesses to react to change."
- APMG International, "AgilePM® Agile Project Management Handbook v2.0," 2014, Chapter 4, Principle 8, Page 21. The principle "Build incrementally from firm foundations" explicitly addresses the need to accommodate change.
Keep practicing
Take the free AGILEPM-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-FOUNDATION practice questions
- Question 1Which of the following statements about diverse teams are true? Increased creativity and …
- Question 2Which statement applies to the DSDM process?
- Question 3Which technique allows for tes'ng the achievailability of objec'ves?
- Question 4What role, ideally, should be independent of the outcome to be achieved in a Facilitated …
- Question 5How does the Post-Project phase add value to a project?
- Question 6Which of the following statements about posi've characteris'cs of an effec've change team …