AGILEPM-FOUNDATION practice question 4 of 35
What role, ideally, should be independent of the outcome to be achieved in a Facilitated Wordshop?
Full set: 150 questionsThe Workshop Facilitator is responsible for managing the workshop process and guiding participants to achieve the workshop's objectives. To be effective, the Facilitator must remain neutral and independent of the workshop's content and outcome. Their focus is on ensuring effective communication, collaboration, and decision-making, rather than contributing to or influencing the final decisions. The other roles listed are all stakeholders with a vested interest in the specific outcome of the workshop.
A. Business Analyst: This role is a key participant, often responsible for gathering and analyzing requirements, and therefore has a direct interest in the outcome.
C. Business Ambassador: This role represents the business users and provides detailed user-level input, making them inherently invested in the outcome.
D. Business Visionary: This role is responsible for the overall business vision and direction of the project, making their interest in the outcome fundamental.
- Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. Chapter 16, DSDM Products, Section 16.2.2 Facilitated Workshops, p. 88. "The Workshop Facilitator... is responsible for managing the workshop process and is independent of the outcome."
- Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. Appendix A: Roles and Responsibilities, Section A.10 Workshop Facilitator, p. 118. "The Facilitator is a neutral role..."
Keep practicing
Take the free AGILEPM-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-FOUNDATION practice questions
- Question 1Which of the following statements about diverse teams are true? Increased creativity and …
- Question 2Which statement applies to the DSDM process?
- Question 3Which technique allows for tes'ng the achievailability of objec'ves?
- Question 5How does the Post-Project phase add value to a project?
- Question 6Which of the following statements about posi've characteris'cs of an effec've change team …
- Question 7Which statement about change is correct for DSDM?