AGILEPM-FOUNDATION practice question 31 of 35

Iden'fy the missing words in the following statement. In projects, especially when using non-agile methods, governance olen seems to focus on [ ? ].

Full set: 150 questions
Answer options
A: Process and tools
B: Comprehensive documenta'on
C: Contract nego'a'on
D: Following a plan Correct answer
Correct Answer:
D. Following a plan
Explanation

Traditional, non-agile project management methods are characterized by extensive upfront planning. Consequently, governance and control in these environments focus heavily on monitoring progress against that detailed, pre-defined plan. Success is often measured by adherence to the plan's schedule, budget, and scope. Agile governance, in contrast, focuses on delivering value and adapting to change.

Why Incorrect

Process and tools: While part of traditional governance, "following a plan" is the overarching principle that dictates the use of specific processes and tools. Comprehensive documentation: This is an output and a tool used to enforce the plan, but the primary focus of governance is the plan itself. Contract negotiation: This is a specific activity, often done at the start, rather than the continuous focus of project governance.

References

Agile Business Consortium. (2017). AgilePM® Agile Project Management Handbook v2.0. Chapter 4, Section 4.8 Principle 7: Demonstrate Control, p. 24. "Traditionally, project control is exercised by monitoring progress against a detailed plan created at the start of the project."