AGILEPM-FOUNDATION practice question 20 of 35

The Product Owner has iden'fied the need for staff training, to ensure the value from the evolving product is fully realized. Which role should the Product Owner discuss this with?

Full set: 150 questions
Answer options
A: Business Visionary
B: Business Sponsor Correct answer
C: Project Manager
D: Scrum Master
Correct Answer:
B. Business Sponsor
Explanation

The Business Sponsor is the project's champion, responsible for the Business Case, budget, and overall benefits realization. The need for staff training is directly linked to ensuring the business can use the new product effectively and thus realize the value promised in the Business Case. Since training often requires funding and is a strategic business decision to ensure project success, the Business Sponsor is the appropriate authority to consult. They hold the ultimate accountability for ensuring the project delivers its intended business value.

Why Incorrect

A. The Business Visionary provides the high-level strategic vision but is not responsible for the project's budget or detailed benefits realization activities like training.
C. The Project Manager is focused on the day-to-day delivery of the solution, not on funding or managing business-side change activities like user training.
D. The Scrum Master is a role from the Scrum framework, not AgilePM. The equivalent role (Team Leader/DSDM Coach) focuses on process and team performance.

References

- Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. Chapter 6, The DSDM People - DSDM Roles and Responsibilities, Section 6.3.1, p. 34. The Business Sponsor is "responsible for the Business Case and project budget throughout" and "ensuring that the business can implement the changes required to realise the benefits."