What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspec've, how the project will be organized and planned?
Full set: 150 questionsThe Management Approach Definition (MAD) is the specific DSDM product that outlines how the project will be managed from start to finish. It details the project management processes, including how the project is organized (roles and responsibilities), planning and control strategies, quality management, risk management, and stakeholder communication. It essentially defines the 'rules of engagement' for the management of the project, tailored to its specific needs.
A. The Foundation Summary is a high-level snapshot of all foundation products, created at the end of the Foundations phase, not the detailed management approach itself.
B. The Delivery Plan provides the high-level schedule for project Increments and their constituent Timeboxes, focusing on the 'when' rather than the overall management approach.
C. The Terms of Reference is a pre-project product used to scope and justify the Feasibility and Foundations phases, not to define the management of the entire project.
Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook DSDM® Atern®. Version 2.0. Chapter 14: DSDM Products, Section: Management Approach Definition, p. 90. "This product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organised and planned."
Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook DSDM® Atern®. Version 2.0. Appendix C: Products - Purpose, Table C.1, p. 138. (Summarizes the purpose of the MAD and distinguishes it from other products).
Keep practicing
Take the free AGILEPM-FOUNDATION practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-FOUNDATION practice questions
- Question 1Which of the following statements about diverse teams are true? Increased creativity and …
- Question 2Which statement applies to the DSDM process?
- Question 3Which technique allows for tes'ng the achievailability of objec'ves?
- Question 4What role, ideally, should be independent of the outcome to be achieved in a Facilitated …
- Question 5How does the Post-Project phase add value to a project?
- Question 6Which of the following statements about posi've characteris'cs of an effec've change team …