When ini'ally crea'ng MoSCoW priori'es, what is the primary focus?

Full set: 150 questions
Answer options
A: Project priori'es Correct answer
B: Project increment priori'es
C: Timebox priori'es
D: Itera've Development priori'es
Correct Answer:
A. Project priori'es
Explanation

When first applying MoSCoW, the focus is on prioritizing the full list of requirements for the entire project. This creates the baseline Prioritised Requirements List (PRL). This project-level prioritization ensures that the most critical features for business success (Must Haves) are identified early. Priorities for specific increments and timeboxes are determined later, drawing from this initial project-level list. This approach provides a strategic overview of what is essential for the minimum usable subset of the solution.

Why Incorrect

B. Project increment priorities are derived from the overall project priorities and are established later, just before the start of a specific increment.
C. Timebox priorities are the most granular level, selected from the increment's backlog at the start of each Timebox to be worked on immediately.
D. Iterative Development is the process used to build the solution; it is not a level of prioritization itself.

References

Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. DSDM Consortium. Chapter 10, Section 10.3, p. 50. ("At the project level, MoSCoW is used to agree the priority of requirements with the business.")

Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. DSDM Consortium. Chapter 14, Section 14.16 (Prioritised Requirements List), p. 90. (Describes the PRL as a project-level product baselined at the end of the Foundations phase).