AGILEPM-FOUNDATION practice question 35 of 35

Which of the following is NOT a Project Ar'fact relevant to Financial Governance?

Full set: 150 questions
Answer options
A: Project Review Report
B: Sprint Review Record Correct answer
C: Founda'on Summary
D: Feasibility Assessment
Correct Answer:
B. Sprint Review Record
Explanation

The Feasibility Assessment, Foundation Summary, and Project Review Report are all official AgilePM artifacts directly linked to financial governance. They are used to establish the initial business case, confirm its viability after the Foundations phase, and review ongoing progress against it, respectively. A "Sprint Review Record" is not a defined AgilePM artifact. AgilePM uses Timeboxes, not Sprints (a Scrum term), and the closest equivalent, the Timebox Review Record, focuses on product feedback rather than financial governance.

Why Incorrect

A. Project Review Report: This report is used to assess the continuing viability of the project at the end of an increment, which is a key financial governance activity.
C. Founda'on Summary: This artifact confirms the project's business case and justification after the Foundations phase, forming a baseline for ongoing financial governance.
D. Feasibility Assessment: This document provides the initial business justification and is the first step in the project's financial governance, determining if the project is worthwhile.

References

- Agile Business Consortium. (2016). AgilePM® Agile Project Management Handbook v2.0. Appendix A: Products, Pages 147-162. (Note: "Sprint Review Record" is not listed as an AgilePM product).

- Agile Business Consortium. (2016). AgilePM® Agile Project Management Handbook v2.0. Chapter 16, Section 16.5, Page 102 (describes the Project Review Report's role in assessing viability).