AGILEPM-FOUNDATION practice question 33 of 35

Which of the following statements about a communication plan are true? Same overall format for all change initiatives. Content will differ depending on the scale and complexity of change.

Full set: 150 questions
Answer options
A: Only 1 is true.
B: Only 2 is true. Correct answer
C: Both 1 and 2 are true.
D: Neither 1 nor 2 is true.
Correct Answer:
B. Only 2 is true.
Explanation

A communication plan must be tailored to the specific needs of the change initiative. Statement 2 is correct because the content, channels, and frequency of communication are directly dependent on the project's scale, complexity, and the stakeholders involved. Statement 1 is incorrect because AgilePM emphasizes tailoring and adaptation over rigid, one-size-fits-all formats. While a template may be used as a starting point, the plan's structure and format should be appropriate for the specific context of the change.

Why Incorrect

A. This is incorrect because statement 1 is false. A single, unchangeable format for all initiatives is contrary to the agile principle of tailoring the approach to the project.
C. This is incorrect because statement 1 is false. A rigid communication plan format is not suitable for the varying needs of different change initiatives.
D. This is incorrect because statement 2 is a fundamental principle of effective communication management; the plan's content must be relevant to the specific change.

References

1. APMG International, AgilePM® Agile Project Management Handbook v2. (Princes Risborough: DSDM Consortium, 2014), p. 128, Section 18.4. The handbook states communication must be "appropriate for the recipients," which implies tailoring content and format.

2. APMG International, AgilePM® Agile Project Management Handbook v2. (Princes Risborough: DSDM Consortium, 2014), p. 10, Principle 2 "Collaborate". Effective collaboration requires communication tailored to the audience and situation, not a rigid format.