AGILEPM-FOUNDATION practice question 15 of 35

Which project role is responsible for mi'ga'ng the risk if there is a lack of commitment in the business opportunity? A. Business Sponsor

Full set: 150 questions
Answer options
A: Business Visionary Correct answer
B: Business Advisor
C: Business Consor'um
Correct Answer:
A. Business Visionary
Explanation

The Business Sponsor is the project champion and is ultimately responsible for the project's business case, including securing funding and confirming that the project remains a viable and worthwhile investment. A lack of commitment to the business opportunity represents a fundamental risk to the project's viability and justification. Therefore, it is the Business Sponsor's responsibility to own and mitigate this high-level business risk, ensuring continued support and commitment from the organization.

Why Incorrect

B. The Business Visionary defines the business vision but does not own the business case or funding; their focus is on ensuring the solution meets business needs.
C. The Business Advisor provides specialist input from a user or business perspective but does not have overall responsibility for the project's business justification.
D. "Business Consortium" is not a defined role within the AgilePM framework. It is a generic term for a group of business stakeholders.

References

Agile Business Consortium. (2014). AgilePM® Agile Project Management Handbook v2.0. Section 6.4.1, "Business Sponsor," states this role is "responsible for the Business Case and project funding" and is the "project champion."