AGILEPM-FOUNDATION practice question 29 of 35

Which should always be the first step in the Con'nuous Change Management Cycle? A. Ideas.

Full set: 150 questions
Answer options
A: Priori'za'on.
B: Discovery.
C: Ac'on. Correct answer
Correct Answer:
C. Ac'on.
Explanation

The Continuous Change Management Cycle is a model that illustrates an iterative approach to managing change. The cycle begins with 'Discovery', which is the phase for understanding the current situation, identifying the need for change, and gathering information and insights. This initial step is crucial for correctly diagnosing the problem or opportunity before moving on to generating ideas, prioritizing them, and taking action. It sets the foundation for all subsequent activities in the cycle.

Why Incorrect

A. Ideas: Generating ideas for solutions or improvements typically follows the initial Discovery phase, where the problem or opportunity is first understood.
B. Prioritization: Prioritization of ideas or actions occurs after they have been generated and evaluated, which happens after the Discovery phase.
D. Action: Action is the implementation phase of the cycle, which comes after Discovery, idea generation, and prioritization have been completed.

References

- Melville, C., et al. (2015). The Effective Change Manager's Handbook. Kogan Page. (Chapter 2, Figure 2.10, 'A continuous change management cycle', clearly shows 'Discovery' as the first of the four repeating stages, followed by Ideas, Prioritization, and Action).

- APMG International. (2015). Change Management Foundation Courseware. (The module on 'Change and the Organization' introduces models of change, including the continuous cycle, where understanding the current state is the starting point).