AGILEPM-PRACTITIONER practice question 12 of 25
Which 2 individuals would be suitable for the role of Workshop Facilitator?
Full set: 185 questionsThe key characteristic of a Workshop Facilitator is neutrality regarding the workshop's topic and outcome. They manage the process, not the content. The Marketing Director and IT Operations Manager are the parties in conflict and are therefore not neutral. The Team Leader and Project Manager are ideal candidates for the facilitator role. Their positions are focused on project process and delivery, allowing them to remain impartial and guide the discussion towards a resolution without taking a side.
B. The IT Operations Manager is a party to the conflict and cannot be a neutral facilitator.
C. The Marketing Director is a party to the conflict and cannot be a neutral facilitator.
D. A Software Developer may have a technical bias and may also lack the specific skills or authority to manage a workshop involving senior stakeholders.
APMG International, "AgilePM® Agile Project Management Handbook v2.0," 2014, p. 118. (Chapter 16, Facilitated Workshops). The handbook states, "The key attribute of a Facilitator is their independence from the topic being discussed... The role is often filled by the Project Manager or the Team Leader."
Keep practicing
Take the free AGILEPM-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-PRACTITIONER practice questions
- Question 1The Legal Specialist has reviewed the plans for the rebranding work and has assessed how …
- Question 2The Solution Development Team are progressing through the first Structured Timebox. What …
- Question 3Using the information provided in the additional information, answer the following questi…
- Question 4Using the information provided in the additional information, answer the following questi…
- Question 5Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate So…
- Question 6During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome …