AGILEPM-PRACTITIONER practice question 11 of 25

How should the Project Manager assist the electricians to deliver the wiring?

Full set: 185 questions
Answer options
A: Provide separate electricians' rooms so they can focus on their work.
B: Hold a weekly meeting for electricians so they can report on progress.
C: Encourage the Business Ambassador to be available to discuss location of electrical sockets. Correct answer
D: Produce a detailed design of all electrical socket locations, to be approved by the Technical Co- ordinator.
Correct Answer:
C. Encourage the Business Ambassador to be available to discuss location of electrical sockets.
Explanation

The Project Manager's primary role includes facilitating communication and removing impediments for the Solution Development Team. The location of electrical sockets is a business requirement that needs input from a business representative. By ensuring the Business Ambassador is available to the electricians, the Project Manager removes a potential blocker, enables timely decision-making, and ensures the delivered solution meets the business need. This is a classic example of a Project Manager acting as a facilitator to keep the project moving forward effectively.

Why Incorrect

A. Providing separate rooms promotes isolation and contradicts the AgilePM principle of Collaboration and rich communication.
B. AgilePM favors daily stand-ups for progress updates, not more formal, less frequent weekly meetings which can delay issue resolution.
D. The Project Manager does not create detailed designs; this is the responsibility of the Solution Development Team.

References

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 28 (Chapter 6: Roles and Responsibilities - Project Manager). The PM is responsible for "Facilitating the team’s progress

removing blockers".

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 17 (Chapter 4: The Principles - Communicate continuously and clearly). The PM's action directly supports this principle.

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 31 (Chapter 6: Roles and Responsibilities - Business Ambassador). The BA is the "main decision-maker" for business requirements.

Scroll to Top