AGILEPM-PRACTITIONER practice question 10 of 25

If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?

Full set: 185 questions
Answer options
A: Present own interpretation of what the system should include.
B: Present the group with a predefined specification of what should be included.
C: Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue. Correct answer
D: Agree to disagree, and close the workshop acknowledging that all participants are entitled to their own view.
E: Prepare a report describing the outcome of the workshop. Correct answer
Correct Answer:
C. Facilitate the creation of a list of actions to be carried out after the workshop, to resolve the issue.; E. Prepare a report describing the outcome of the workshop.
Explanation

When a group cannot reach an agreement during a workshop, the Facilitator's role is to guide them to a productive conclusion. A primary technique is to stop the debate on the unresolved topic and facilitate the creation of a list of specific actions to resolve the issue after the workshop, assigning owners and deadlines (C). This maintains momentum. Subsequently, the Facilitator must accurately document the workshop's outcomes in a report (E), which would include points of agreement, the specific nature of the disagreement, and the agreed-upon actions for resolution.

Why Incorrect

A. The Facilitator must remain neutral and not impose their own views or interpretations on the content of the solution.
B. Presenting a predefined specification undermines the collaborative purpose of the workshop and violates the Facilitator's neutrality.
D. "Agreeing to disagree" without a plan for resolution is a failure of the workshop, which aims to move the project forward.

References

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 78

Section 11.6

"During the workshop." This section describes the facilitator's role in managing group dynamics and ensuring a productive outcome

which includes managing unresolved issues by parking them with agreed follow-up actions.

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 79

Section 11.7

"Follow-up." This section details the importance of documenting and circulating the workshop report promptly.