AGILEPM-PRACTITIONER practice question 9 of 25

Xan Insurance Company operates from one location - a large, open-plan office in the centre of a city. Those employees that will be working within the Solution Development Team are all based in this office but work at different ends of the office in separate departments. What action should the Project Manager suggest to ensure the most effective collaboration of the Solution Development Team?

Full set: 185 questions
Answer options
A: Create an email group for the Solution Development Team to collaborate on ideas.
B: Set up a telephone or video conferencing facility so that all members of the team can collaborate effectively.
C: Relocate these employees to a new project area, with a number of desks where the Solution Development Team can sit together. Correct answer
D: No action required as these employees are located in the same office.
Correct Answer:
C. Relocate these employees to a new project area, with a number of desks where the Solution Development Team can sit together.
Explanation

AgilePM strongly advocates for rich, face-to-face communication to foster collaboration, speed up decision-making, and enable 'osmotic communication' (where team members overhear information relevant to their work). Even though the team is in the same building, being at different ends of an office creates a communication barrier. The most effective action is to co-locate the Solution Development Team in a dedicated project area or 'war room'. This physical proximity is the best enabler for the close, continuous collaboration that is fundamental to agile development.

Why Incorrect

A. Email is a poor medium for collaboration; it is slow, asynchronous, and lacks the richness of face-to-face conversation.
B. Conferencing facilities are designed for geographically distributed teams, not for a team located in the same building.
D. Being in the same office is not sufficient; physical separation, even within one building, hinders the high-bandwidth communication agile teams require.

References

APMG International

"AgilePM® Agile Project Management Handbook v2.0

" 2014. Chapter 15: Communication

Section 15.3 Rich Communication

p. 107. (This section explicitly states

"The ideal is for the Solution Development Team to be co-located... This enables the richest possible communication").

APMG International

"AgilePM® Agile Project Management Handbook v2.0

" 2014. Chapter 4: The DSDM Principles

Principle 6: Communicate Continuously and Clearly

p. 20. (This principle is best supported by co-location and face-to-face interaction).