AGILEPM-PRACTITIONER practice question 8 of 25

Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?

Full set: 185 questions
Answer options
A: Details of which areas will require seeding in order to become lawn, and which are to become planted borders, should be captured.
B: The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.
C: The scope of the project should be agreed before moving into the Foundations phase. Correct answer
D: The responsibility for setting the priority of each of the requirements identified should be assigned to the Project Manager.
E: Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements. Correct answer
Correct Answer:
C. The scope of the project should be agreed before moving into the Foundations phase.; E. Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.
Explanation

During the Feasibility phase, the goal is to determine if the project is viable at a high level. This involves agreeing on the high-level scope (C) to provide a basis for the decision to proceed to the Foundations phase. It is also critical to identify any absolute constraints or non-negotiable requirements early on. Regulatory obligations are a primary example of such constraints and must be treated as 'Must Have' requirements from the outset (E), as they directly impact the project's viability, timeline, and cost. Capturing these elements provides a realistic basis for the initial business case and outline plan.

Why Incorrect

A. This level of detail is too granular for the Feasibility phase and is more appropriate for the Foundations phase or a specific Development Timebox.
B. While these items could be 'Must Haves', assigning this priority in Feasibility is presumptive. Their necessity would be confirmed in Foundations based on the business case.
D. The Business Visionary, supported by the Business Ambassador(s), is responsible for setting requirement priorities, not the Project Manager.

References

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

pp. 27-28. (Describes the Feasibility phase purpose as establishing a high-level view of scope and business case

leading to a decision to proceed).

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 69. (Section 12.4 explains that 'Must Haves' can be defined by business or legal needs

confirming regulatory items are typically Must Haves).

APMG International

"AgilePM® Agile Project Management Handbook v2

" 2014

p. 41. (Figure 8.2 shows the Business Visionary is responsible for requirement prioritisation).