AGILEPM-PRACTITIONER practice question 8 of 25
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
Full set: 185 questionsDuring the Feasibility phase, the goal is to determine if the project is viable at a high level. This involves agreeing on the high-level scope (C) to provide a basis for the decision to proceed to the Foundations phase. It is also critical to identify any absolute constraints or non-negotiable requirements early on. Regulatory obligations are a primary example of such constraints and must be treated as 'Must Have' requirements from the outset (E), as they directly impact the project's viability, timeline, and cost. Capturing these elements provides a realistic basis for the initial business case and outline plan.
A. This level of detail is too granular for the Feasibility phase and is more appropriate for the Foundations phase or a specific Development Timebox.
B. While these items could be 'Must Haves', assigning this priority in Feasibility is presumptive. Their necessity would be confirmed in Foundations based on the business case.
D. The Business Visionary, supported by the Business Ambassador(s), is responsible for setting requirement priorities, not the Project Manager.
APMG International
"AgilePM® Agile Project Management Handbook v2
" 2014
pp. 27-28. (Describes the Feasibility phase purpose as establishing a high-level view of scope and business case
leading to a decision to proceed).
APMG International
"AgilePM® Agile Project Management Handbook v2
" 2014
p. 69. (Section 12.4 explains that 'Must Haves' can be defined by business or legal needs
confirming regulatory items are typically Must Haves).
APMG International
"AgilePM® Agile Project Management Handbook v2
" 2014
p. 41. (Figure 8.2 shows the Business Visionary is responsible for requirement prioritisation).
Keep practicing
Take the free AGILEPM-PRACTITIONER practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other AGILEPM-PRACTITIONER practice questions
- Question 1The Legal Specialist has reviewed the plans for the rebranding work and has assessed how …
- Question 2The Solution Development Team are progressing through the first Structured Timebox. What …
- Question 3Using the information provided in the additional information, answer the following questi…
- Question 4Using the information provided in the additional information, answer the following questi…
- Question 5Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate So…
- Question 6During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome …
