The prime purpose of configuration management is to:

Full set: 409 questions
Answer options
A: ensure the traceability and integrity of the delivered product or products Correct answer
B: minimise the impact of changes on the scope of the project
C: ensure that the final product meets the needs of the business as defined by key stakeholders.
D: maximise the impact of agreed enhancements to the project deliverables
Correct Answer:
A. ensure the traceability and integrity of the delivered product or products