APM-PFQ practice question 20 of 35

What is the main reason for having an extended life cycle?

Full set: 409 questions
Answer options
A: Allow the project to have extra time to ensure that that there is enough capacity to realise benefits.
B: Allow upfront planning for any supplemental activities and incorporate additional considerations for benefits realisation. Correct answer
C: Allow time for stakeholders to decide how they will use the output to best effect that will realise benefits.
D: Allow extra funding to be applied to the project to ensure that sufficient resources exist to maximise benefits realisation.
Correct Answer:
B. Allow upfront planning for any supplemental activities and incorporate additional considerations for benefits realisation.