APM-PFQ practice question 25 of 35

When the project progresses through the life cycle. which one of the following aspects would be expected to occur?

Full set: 409 questions
Answer options
A: The accuracy of the estimate reduces and the level of contingency requirement increases.
B: The accuracy of the estimate increases and the level of contingency requirement reduces. Correct answer
C: The accuracy and level Of contingency requirement both increase.
D: The accuracy and level of contingency requirement both reduce.
Correct Answer:
B. The accuracy of the estimate increases and the level of contingency requirement reduces.