APM-PFQ practice question 15 of 35

Which of the following would be considered as the main purpose of a project management plan?

Full set: 409 questions
Answer options
A:

A. To provide a documented account of the outcomes of the planning process.

B:

B. To enable agreement between the project sponsor and project manager with regard to project budget, resource requirements and timescale.

C:

C. To provide record of how the project was planned, for archiving in the organisation's lessons learned.

D:

D. To identify and record the projects intended financial spend over the period of project delivery.

Correct Answer:
<P>B</P>