APM-PMQ practice question 6 of 10

Which of the activities below would provide final assurance of a project?

Full set: 40 questions
Answer options
A: Troubleshooting a technical fault.
B: Allocation and approval of the project budget.
C: Testing of a product. Correct answer
D: Developing organizational policies.
Correct Answer:
C. Testing of a product.
Explanation

Product testing ensures the deliverables meet the intended specifications and are ready for deployment, which is the final assurance step before project closure.
Reference: PMBOK Guide (Quality Assurance and Validation).