APM-PMQ practice question 5 of 10

You are the project manager on a construction project for a client in the defence sector. The client has strict regulatory requirements and expects a high level of control and governance throughout the project. Which life cycle would be most suitable?

Full set: 40 questions
Answer options
A: Iterative
B: Hybrid
C: Incremental
D: Linear Correct answer
Correct Answer:
D. Linear
Explanation

The Linear (or Waterfall) lifecycle is the most suitable for projects that require high levels of governance, control, and strict adherence to regulatory requirements. Applicability: Linear project management focuses on predefined stages (e.g., requirements, design, implementation) that align with regulatory needs. Advantages: It allows detailed documentation, structured review processes, and adherence to pre- approved plans, ensuring compliance with defence sector standards. Alternative Options: Iterative and incremental approaches are less appropriate due to the less structured nature of deliverable evolution in these methods.

Scroll to Top