APM-PMQ practice question 2 of 10
You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register. Which of the following statements about the project business case is true?
Full set: 40 questionsCorrect Answer:
A. The business case contained assumptions which should be reviewed against the cost-benefit
analysis.
Explanation
The business case should contain assumptions, and in this scenario, assumptions about ground conditions need to be reviewed against the cost-benefit analysis to reassess project feasibility.
Reference: PMBOK Guide (Business Case Review and Risk Management).
Keep practicing
Take the free APM-PMQ practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other APM-PMQ practice questions
- Question 1Which of the following statements does not describe the importance of linking projects to…
- Question 4During a project review, which of the following would be the best indicator of how the pr…
- Question 5You are the project manager on a construction project for a client in the defence sector.…
- Question 6Which of the activities below would provide final assurance of a project?
- Question 7You are a project manager leading a newly formed project team. Which factor should NOT in…
- Question 8You are the project manager of a promotional campaign project that’s currently in the dev…
