APM-PMQ practice question 2 of 10

You are in the design phase of a project to deliver offices on a newly acquired plot of land. You have now completed extra surveys and discovered that the ground conditions are a lot softer than expected, meaning the design and delivery will be far more complex and costly. You did not account for this in your risk register. Which of the following statements about the project business case is true?

Full set: 40 questions
Answer options
A: The business case contained assumptions which should be reviewed against the cost-benefit analysis. Correct answer
B: There is a strong strategic case for the project to continue, even if it is late or over budget.
C: The business case has already been signed off, so the project should continue as planned.
D: The project sponsor did not properly evaluate all available options in the business case.
Correct Answer:
A. The business case contained assumptions which should be reviewed against the cost-benefit analysis.
Explanation

The business case should contain assumptions, and in this scenario, assumptions about ground conditions need to be reviewed against the cost-benefit analysis to reassess project feasibility.
Reference: PMBOK Guide (Business Case Review and Risk Management).