BIM_MGT_101 practice question 10 of 10
A BIM manager is reviewing a consultant’s architectural model before the next coordination milestone. The project requires each model to conform to a…
Choose your answer, then check it against the explanation.
A BIM manager is reviewing a consultant’s architectural model before the next coordination
milestone. The project requires each model to conform to a defined naming convention, include
COBie parameters, and populate shared parameters according to the Model Element Table. The BIM
manager notices that several elements are missing metadata and that some naming is inconsistent.
Which step best supports a systematic evaluation of completeness and compliance with project
standards?
Question 10 of 10
Keep practicing
Take the free BIM_MGT_101 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other BIM_MGT_101 practice questions
- Question 1A team member accidentally unpinned and dragged a linked CAD file, and it is no longer al…
- Question 3During early coordination on a hospital project, the BIM manager runs a general clash det…
- Question 4Which of the following would typically be included in an AECO BIM data handover package a…
- Question 7A multidisciplinary healthcare project has multiple firms contributing to a federated mod…