BIM_MGT_101 practice question 3 of 10
During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash…
Choose your answer, then check it against the explanation.
During early coordination on a hospital project, the BIM manager runs a general clash detection
between all models and generates over 3,000 clash results. Many are low-priority issues, such as
wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high-
impact clashes between structural, MEP, and architecture in specific zones.
For the BIM manager, what is the most appropriate next step to align clash reporting with the
project’s coordination strategy?
Question 3 of 10
Keep practicing
Take the free BIM_MGT_101 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other BIM_MGT_101 practice questions
- Question 1A team member accidentally unpinned and dragged a linked CAD file, and it is no longer al…
- Question 4Which of the following would typically be included in an AECO BIM data handover package a…
- Question 7A multidisciplinary healthcare project has multiple firms contributing to a federated mod…
- Question 10A BIM manager is reviewing a consultant’s architectural model before the next coordinatio…