BIM_MGT_101 practice question 3 of 10

During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash…

Choose your answer, then check it against the explanation.

During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high- impact clashes between structural, MEP, and architecture in specific zones. For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?