BIM_MGT_101 practice question 3 of 10

During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash…

Full set: 57 questions
During early coordination on a hospital project, the BIM manager runs a general clash detection between all models and generates over 3,000 clash results. Many are low-priority issues, such as wall-grid overlaps and minor duct-ceiling intersections. The project’s clash matrix outlines only high- impact clashes between structural, MEP, and architecture in specific zones. For the BIM manager, what is the most appropriate next step to align clash reporting with the project’s coordination strategy?
Answer options
A: Share the full clash report with all project teams and instruct them to determine and resolve the issues they consider most important.
B: Export the entire clash list into spreadsheet format so project managers can manually sort, review, and prioritize the items by trade.
C: Disable or relax selected non-critical clash rules within the detection software to temporarily reduce the total number of reported issues.
D: Apply the clash matrix to filter out low-priority clashes, adjust detection tolerances where appropriate, and produce reports for each discipline’s scope. Correct answer
Correct Answer:
D. Apply the clash matrix to filter out low-priority clashes, adjust detection tolerances where appropriate, and produce reports for each discipline’s scope.
Explanation

In large-scale projects, running automated clash detection across all elements without scope filters yields thousands of irrelevant false positives, creating operational noise. A BIM Execution Plan (BEP) defines a clash matrix specifying precise tolerances, priority rules, and specific spatial zones for coordination. Applying the clash matrix enables the BIM manager to filter out minor geometric overlaps—such as minor duct-ceiling clearance issues or grid lines—and adjust hard and soft clash tolerances appropriately. By generating targeted reports filtered by discipline, zone, and trade scope, the BIM manager ensures that project teams receive actionable, prioritized clash data directly aligned with the project's predefined coordination strategy.

Why Incorrect

A. Distributing raw, unfiltered clash reports creates confusion, overwhelms trade contractors with minor false positives, and lacks clear prioritization aligned with project strategy.
B. Exporting thousands of unfiltered issues into a spreadsheet transfers manual sorting burdens to project managers without utilizing built-in BIM coordination filtering rules.
C. Temporarily relaxing or disabling rules across the board obscures legitimate high-priority clashes and risks missing critical constructability issues in essential building zones.

References

1. ISO 19650-2:2018 Section 5.6 "Production of information - Collaborative production of information and spatial coordination".

2. Autodesk Construction Cloud / Model Coordination Documentation: "Clash Detection

Clash Matrix

and Tolerance Settings". https://help.autodesk.com/view/COLLAB/ENU/

3. Penn State Computer Integrated Construction Research Program

"BIM Project Execution Planning Guide"

Version 2.2

Section 3.2 "Clash Detection and Coordination".