BIM_MGT_101 practice question 4 of 10
Which of the following would typically be included in an AECO BIM data handover package at project closeout?
Full set: 57 questionsAt project completion, the primary BIM deliverable handed over to the owner or facility manager is the record model (or as-built BIM). Record models integrate all design changes, field modifications, and approved submittals accumulated during construction, along with detailed asset data required for Facilities Management (FM) and Operations and Maintenance (O&M). Standard frameworks like ISO 19650 and COBie mandate that record models contain accurate non-geometric attributes—such as equipment serial numbers, warranty details, and maintenance schedules—embedded directly within the BIM elements. Handing over finalized record models with embedded asset data ensures the facility management team can effectively operate, maintain, and manage the physical asset throughout its lifecycle.
A. Internal meeting notes are temporary administrative records used during active coordination and are not required or useful for long-term facility operations.
B. Federated design models used during construction clash detection represent intermediate work-in-progress state models, not the finalized as-built facility conditions required at handover.
C. Temporary 3D saved views created solely for spatial clash analysis during model coordination are transient working views rather than standardized operational closeout deliverables.
1. ISO 19650-2:2018 Organization and digitization of information about buildings and civil engineering works — Part 2: Delivery phase of the assets
Section 5.8 "Handover of asset information".
2. Autodesk BIM 360 / ACC Documentation: "Managing Asset Data for Facilities Handover and Project Closeout". https://help.autodesk.com/view/BIM360D/ENU/
3. National Institute of Building Sciences (NIBS)
National BIM Standard - United States (NBIMS-US) V3
Section 4.2 "COBie and Asset Data Handover".
Keep practicing
Take the free BIM_MGT_101 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other BIM_MGT_101 practice questions
- Question 1A team member accidentally unpinned and dragged a linked CAD file, and it is no longer al…
- Question 3During early coordination on a hospital project, the BIM manager runs a general clash det…
- Question 7A multidisciplinary healthcare project has multiple firms contributing to a federated mod…
- Question 10A BIM manager is reviewing a consultant’s architectural model before the next coordinatio…