B. Phased
Explanation

A phased rollout is an implementation strategy where a change is introduced to different parts of an organization in a planned sequence. Rolling out a new software application "one department at a time" is a classic example of this approach. This strategy allows the organization to test the implementation process, gather feedback, and make adjustments in a controlled manner before deploying the change to the next group. It helps manage risk and reduces the initial support burden compared to a "Big Bang" approach where everyone transitions at once.

Why Incorrect

A. A Big Bang strategy involves implementing the change for everyone across the entire organization at the same time.
C. Voluntary Adoption implies that departments or users can choose if and when to adopt the new software, which is not stated here.
D. Incremental/iterative releases refer to delivering the software's functionality in small pieces, not the strategy for deploying it to user groups.

References

1. Smith, R., King, D., Sidhu, R., & Skelsey, D. (Eds.). (2015). The Effective Change Manager's Handbook. Kogan Page. (Chapter 14, Section 14.5.2, pp. 360-361, describes different implementation options, defining a phased approach as introducing change to "different business units or locations at different times").

2. APMG International. (2015). Change Management Foundation Courseware. (Syllabus section 4.2, "Options for sequencing change," covers different approaches including phased implementation, big bang, and pilots).

Scroll to Top