CIS-SPM practice question 20 of 25

What Ul Actions are available to link RIDAC records? Choose 2 answers

Full set: 112 questions

Domain Resource Management

Answer options
A: Q Apply Template
B: Convert to RIDAC Correct answer
C: Save as New Template
D: Associate RIDAC Correct answer
E: View RIDAC
Correct Answer:
B. Convert to RIDAC; D. Associate RIDAC
Explanation

The ServiceNow Strategic Portfolio Management (SPM) application provides specific UI Actions to manage the relationships between records. To link RIDAC (Risks, Issues, Decisions, Actions, Changes) records, two primary UI Actions are available.
1. Convert to RIDAC: This action, often seen as "Convert to Risk" on an issue form, transforms one type of record into another (e.g., an issue becomes a risk). This process creates a new RIDAC record and automatically links it to the source entity (like a project), closing the original record.
2. Associate RIDAC: This UI action allows users to link an existing RIDAC record to the current record, such as a project or demand. This establishes a direct relationship without creating a new record.

Why Incorrect

A. Apply Template: This action populates fields on a new or existing record from a pre-configured template; it does not link records together.
C. Save as New Template: This action creates a template from the current record for future use. It is a configuration action, not a linking action.
E. View RIDAC: This is a navigational action used to open and display the details of an existing RIDAC record, not to create an association.

References

1. ServiceNow Product Documentation - Convert an issue to a risk: This document explicitly describes the "Convert to Risk" UI Action. It states, "When you convert an issue to a risk, the issue is closed and a new risk is created. The new risk is automatically associated with the project." This confirms the linking function of the conversion process. (ServiceNow, Project Workspace, "Convert an issue to a risk").

2. ServiceNow Product Documentation - Associate a RIDAC item with a project: This document details the "Associate RIDAC" functionality. It explains, "You can associate existing risks, issues, decisions, actions, and changes (RIDAC) to your project from the project workspace." This directly supports the "Associate RIDAC" option as a method for linking records. (ServiceNow, Project Workspace, "Associate a RIDAC item with a project").