CPIM-PART-2 practice question 20 of 25
In which of the following environments is capable-to-promise (CTP) more appropriate than available- to-promise (ATP)?
Full set: 151 questionsCapable-to-promise (CTP) is a method of order promising that considers both material and capacity availability. CTP is more appropriate than available-to-promise (ATP), which only considers material availability, in environments where the production process is complex, customized, or resource- intensive, and where the demand is uncertain or variable. CTP can provide more accurate and realistic delivery dates, as well as optimize the use of resources and reduce inventory costs. Among the options given, specialty chemicals packaged and shipped to order is the most suitable environment for CTP. This is because specialty chemicals are often produced in small batches or on demand, according to the specific requirements and p
of each customer. Therefore, the
production process requires high flexibility and customization, as well as careful coordination of
materials and capacity. The demand for specialty chemicals may also vary depending on the market
conditions and customer needs. CTP can help the company to promise delivery dates that take into
account the availability of both materials and capacity, as well as the production lead time and
transportation time.
The other options are less suitable for CTP, as they are more likely to use standard or mass
production processes, where the products are made in large quantities or in advance, and where the
demand is more stable or predictable. In these environments, ATP may be sufficient to promise
delivery dates based on material availability alone, without considering capacity constraints.
Reference : What is a Capable-to-Promise System (CTP System … - Techopedia; Order promising -
Supply Chain Management | Dynamics 365; Capable to Promise (CTP) (MRP and Supply Chain
Planning Help) - Oracle; Calculate sales order delivery dates using CTP - Supply Chain ….
Keep practicing
Take the free CPIM-PART-2 practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CPIM-PART-2 practice questions
- Question 1In a lean environment, one uses material requirements planning (MRP) processing primarily…
- Question 2Up-to-date information about production order status is required to do which of the follo…
- Question 3The results from responding to uncertainty in the supply chain by exaggerating lead times…
- Question 4The capacity requirements plan is used primarily to:
- Question 5Which of the following outcomes is a benefit of mixed-model scheduling?
- Question 6Which of the following tools is used to evaluate the impact that a production plan has on…