CPIM-PART-2 practice question 20 of 25

In which of the following environments is capable-to-promise (CTP) more appropriate than available- to-promise (ATP)?

Full set: 151 questions
Answer options
A: Consumer electronics sold through local retailers
B: Industrial supplies shipped from regional distribution centers (DCs)
C: Packaged foods sold in grocery stores
D: Specialty chemicals packaged and shipped to order Correct answer
Correct Answer:
D. Specialty chemicals packaged and shipped to order
Explanation

Capable-to-promise (CTP) is a method of order promising that considers both material and capacity availability. CTP is more appropriate than available-to-promise (ATP), which only considers material availability, in environments where the production process is complex, customized, or resource- intensive, and where the demand is uncertain or variable. CTP can provide more accurate and realistic delivery dates, as well as optimize the use of resources and reduce inventory costs. Among the options given, specialty chemicals packaged and shipped to order is the most suitable environment for CTP. This is because specialty chemicals are often produced in small batches or on demand, according to the specific requirements and p

References

of each customer. Therefore, the

production process requires high flexibility and customization, as well as careful coordination of

materials and capacity. The demand for specialty chemicals may also vary depending on the market

conditions and customer needs. CTP can help the company to promise delivery dates that take into

account the availability of both materials and capacity, as well as the production lead time and

transportation time.

The other options are less suitable for CTP, as they are more likely to use standard or mass

production processes, where the products are made in large quantities or in advance, and where the

demand is more stable or predictable. In these environments, ATP may be sufficient to promise

delivery dates based on material availability alone, without considering capacity constraints.

Reference : What is a Capable-to-Promise System (CTP System … - Techopedia; Order promising -

Supply Chain Management | Dynamics 365; Capable to Promise (CTP) (MRP and Supply Chain

Planning Help) - Oracle; Calculate sales order delivery dates using CTP - Supply Chain ….