CSSLP practice question 33 of 35
You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?
Full set: 357 questionsResidual risk is a fundamental concept in risk management. It is the amount of risk that remains after an organization has implemented countermeasures or controls to mitigate an identified risk. No control is 100% effective, and it is often not cost-effective to eliminate all risk. Therefore, after applying risk responses such as mitigation, transference, or avoidance, a certain level of risk will persist. This remaining risk is known as residual risk, which the organization must then formally accept, monitor, and manage.
A. This describes an unmitigated or untreated risk, which is the risk in its initial state before any controls are applied, not the risk that remains after.
B. This is incorrect. Residual risk is what remains after a response is applied. A risk that cannot be addressed at all is a different, more extreme condition.
C. This is too absolute. Risk responses are designed to reduce risk. Residual risk is the reduced level of risk, not a risk that is completely unaffected by any response.
1. National Institute of Standards and Technology (NIST). (2012). Guide for Conducting Risk Assessments (NIST Special Publication 800-30, Revision 1). U.S. Department of Commerce. In Section 2.2.5, "Risk Response," the document states, "The risk remaining after risk responses have been implemented is referred to as residual risk." (Page 11, Section 2.2.5).
2. Purdue University. (n.d.). Information Security and Privacy - Risk Management. In the glossary of terms, residual risk is defined as: "The risk that remains after controls are implemented to reduce the inherent risk." Retrieved from Purdue University's Information Security and Policy website.
3. Stoneburner, G., Goguen, A., & Feringa, A. (2002). Risk Management Guide for Information Technology Systems (NIST Special Publication 800-30). U.S. Department of Commerce. The glossary defines residual risk as: "The portion of risk remaining after security measures have been applied." (Page 53, Appendix G).
Keep practicing
Take the free CSSLP practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other CSSLP practice questions
- Question 1Fred is the project manager of the CPS project. He is working with his project team to pr…
- Question 2You work as a system engineer for BlueWell Inc. You want to verify that the build meets i…
- Question 3An asset with a value of $600,000 is subject to a successful malicious attack threat twic…
- Question 4John works as a professional Ethical Hacker. He has been assigned the project of testing …
- Question 5A part of a project deals with the hardware work. As a project manager, you have decided …
- Question 6Information Security management is a process of defining the security controls in order t…