ICYB practice question 16 of 25
Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before money costs and taxes)?
Full set: 120 questionsThe payback period is the time required for the cumulative savings from a project to equal the total initial investment. The total investment includes all initial costs, which are the project investment and the training cost. The calculation must also account for the 4-month delay before savings begin.
1. Total Initial Investment: $23,500 (project) + $2,500 (training) = $26,000.
2. Time to Recoup Investment: $26,000 / $2,500 per month = 10.4 months.
3. Total Payback Period: This 10.4-month period only starts after the initial 4-month delay. Therefore, the total time from the initial investment is 4 months (delay) + 10.4 months (savings period) = 14.4 months.
A. 7.2: This result does not correspond to a correct calculation using the provided project financial data.
B. 10.4: This is the time required to recoup the investment once savings begin, but it incorrectly omits the initial 4-month delay.
D. 28.8: This value is double the correct answer and is likely included as a computational distractor.
1. IASSC Certified Lean Six Sigma Yellow Belt Body of Knowledge (v3.0): The concept of project metrics, including financial evaluation, is a core component of the Measure Phase. Section 3.1.3, "Basic Six Sigma Metrics," covers the fundamental calculations used to assess project performance and financial viability. The payback period is a standard metric in this context.
2. Park, C. S. (2019). Contemporary Engineering Economics (7th ed.). Pearson. Chapter 7, "Payback Period Analysis," defines the payback period as the time it takes for a project's cumulative cash flows to recover the initial investment. The methodology requires accounting for the timing of all cash flows, including initial delays before positive inflows begin. An example on page 298 illustrates that the payback clock starts at time zero, and any period without cash inflow extends the total payback time.
3. MIT OpenCourseWare, Course 15.010 / 15.011, Economic Analysis for Business Decisions, Fall 2004. Lecture notes on "Investment Decisions and Capital Budgeting" explain that the payback period calculation must summate cash flows chronologically until the initial outlay is recovered. This principle confirms that a 4-month period of zero cash inflow must be added to the time required for positive cash flows to cover the investment.
Keep practicing
Take the free ICYB practice test
Ten exam-style questions with answers and explanations, plus the exam facts and study guides.
More questions
Other ICYB practice questions
- Question 1The “Method” category of Root Causes on a Fishbone Diagram is primarily used to generate …
- Question 2The formula Y = f(Xn) is a method of expressing the concept that the output of a process …
- Question 3The “Equipment” category of Root Causes on a Fishbone Diagram would be used primarily use…
- Question 4A Belt has determined that the loan application does not need to be reviewed by accountin…
- Question 5As we identify customer and supplier requirements for a SIPOC we are urged to use the RUM…
- Question 6To minimize waste through the application of Lean Principles we do which of the following?