ISEB-PM1 practice question 31 of 35

A project manager has just been assigned to a new project and has been given the approved project charter. The FIRST thing the project manager must do is:

Full set: 625 questions
Answer options
A: Create a project scope statement.
B: Confirm that all the stakeholders have had input to the scope. Correct answer
C: Analyze project risk.
D: Begin work on a project management plan.
Correct Answer:
B. Confirm that all the stakeholders have had input to the scope.