Company A is launching a new communications satellite system. Resource B was assigned combined projects of design, construction, integration, and launch of the satellite. Resource B's role is that of a:

Full set: 625 questions
Answer options
A: Project manager
B: Portfolio manager
C: Work breakdown manager
D: Program manager Correct answer
Correct Answer:
D. Program manager