ISEB-PM1 practice question 35 of 35

How is the process of collecting requirements defined?

Full set: 625 questions
Answer options
A: Defining and documenting project sponsors' needs to meet the project objectives
B: Defining and documenting stakeholders' needs to meet the project objectives Correct answer
C: Defining and documenting the project teams' needs to meet the project objectives
D: Defining and documenting the project needs to meet the project objectives
Correct Answer:
B. Defining and documenting stakeholders' needs to meet the project objectives