ISEB-PM1 practice question 16 of 35

If a project manager is concerned with gathering, integrating, and disseminating the outputs of all project management processes, she should concentrate on creating a better:

Full set: 625 questions
Answer options
A: WBS.
B: Communications management plan.
C: Project management information system. Correct answer
D: Project scope management plan.
Correct Answer:
C. Project management information system.